Call us on 01202 764 551 webenquiries@greendaleconstruction.com
23rd January 2015

1

24th October 2013

Worshippers at Poole Methodist Church, Poole High Street, are benefitting from an extensive £1.1 million restoration and re-development of the existing church by Dorset Chartered Builders, Greendale Construction Limited.

Phase 1 of the project, which commenced in October 2013, have included re-development of the existing church to form a new community café and a small chapel, with the main church on a new 1st floor to the existing church building.  New community rooms and halls are being formed in a new build to the rear. The existing church has been stripped out and remedial works undertaken to the spire and external stonework. New guttering & bird protection has been put in place and alterations to the front of the building to form two new entrances. A new concrete floor slab and steel frame for the new 1st floor including composite concrete floor has also been completed and new utility services have also been installed.

Greendale Contracts Director, Andy Musselwhite commented: “Greendale Construction Limited have been on site for some months now with this exciting and interesting project. Poole Methodists are making a bold, but decisive step to improve the church and community facilities in the centre of Poole. The complex works include piling works inside the church for the new ground and first floor structure, as well as external stone refurbishment and new glazed entrance.”

We will be adding photos of work chronologically as progress continues.

2 3 4 5 6 7

Progress 27/01/14  These progress shots  show that the Poole Methodist church project is progressing well with the main church area completely cleared to enable piling operations to begin.  The site set up is in place and a major part of the demolitions are complete.

Our Carpenters Nick and Mike are repairing the flat roof areas at very high level.

Pete Marks site manager said: “I’m very pleased with the progress. The project is gaining momentum.”

Poole-Methodist1-300x225 Poole-Methodist2 Poole-Methodist3-300x225 Poole-Methodist4-300x225

Progress 29/05/14

29 may

The Poole Methodist Church project continues with some stunning photos of progress so far. The works have been completed in phases and are to re-develop the existing church to form a new community café, a small chapel, with the main church on a new 1st floor to the existing church building, as well community rooms and halls in a new build to the rear. So far, Greendale have partly demolished the rear halls to allow work to commence, leaving the small hall available for use by the church groups. We have stripped out the existing church and undertaken remedial works to the spire and external stonework. New guttering & bird protection has been put in place and alterations to the front to form 2 new entrances. Piling for new foundations within the existing church – up to 14.5m deep. A new concrete floor slab, and steel frame for the new 1st floor including composite concrete floor. New utility services have also been installed.

29 may 229 may 329 may 429 may 529 may 629 may 7

Progress 22/09/14  These shots taken at Poole Methodist Church show work progressing really well.  In the shot below we can see the existing circular stained glass window and construction of the new mezzanine floor.

Poole Methodist1

Poole Methodist2
Some superb stone work features consisting of matching dressed stone and blue
Lias Purbeck stone forming new entrances.

 

The latest shots, below, show how the work is really taking shape.
Structural openings formed at mezz level for escape and the beautiful dressed new Purbeck stone steps to new grand entrance welcoming from High Street.

Methodist1methodist2

Methodist3

Progress 21/01/15 – Phase 2

Phase 2 works at Poole Methodist Church in Poole High Street are starting well. With the old church halls now demolished the piling works for the new building has started.

Poole Methodist

Updated 13/03/15

As the photos show below, steelwork erection has commenced to Phase 2 of the Poole Methodist Church contract in Poole High Street. This work follows the extensive piling works, associated ground beams and lift pit construction.

methodist1 methodist2

01202 764 551 Email us